The construction of the barrier was carried out within the operation lockout since the beginning of June, the speed of construction was about 8 meters per shift. Ongoing for the assembly, in coordination with DPP, and no special lockout was needed. The entire construction was provided by a team from the Faculty of Civil Engineering. The whole concept has been developed to make assembly as simple and fastest as possible. The aperture is based on a gravel bed on individual oddated concrete foundation strips. The individual parts are attached to them, and they are then joined together. This system allows for quick construction and rapid dismantling if necessary, whether in the case of rescue operations or track maintenance. Another interesting property is that the concrete strips are reinforced with a composite fiberglass mesh instead of steel, which prevents the spread of stray currents around the track. The barrier is designed to minimize visual impact on the environment and yet absorb maximum noise at the wheel-rail contact. The barrier in Hloubětín is made in the basic black-gray hue, but it can also be produced in a number of other colors, according to architectural requirements.
Website novinky.cz had also informed about the noise barrier